Given a project with an estimated effort of 1500 person-hours and a team of 5 people, how many days will it take to complete the project, if each person works 8 hours a day ?
Total effort
$1500$ person-hours
Work per day by team:
$5 \times 8 = 40$ hours/day
Days required
$= \frac{1500}{40}$
$= 37.5$