A $4$-stage pipeline has a stage delay of $150,120,160$ and $140$ ns respectively. Registers that are used between the stages have a delay of $5$ ns. Assuming constant locking rate, the total time required to process $1000$ data items on this pipeline is





Solution

Given,

Number of pipeline stages:

$k=4$

Number of data items:

$n=1000$

Stage delays are:

$150$ ns, $120$ ns, $160$ ns and $140$ ns

Register delay:

$5$ ns

In a pipeline, clock cycle time is decided by the slowest stage.

Slowest stage delay:

$160$ ns

So, pipeline clock cycle time is:

$160+5=165$ ns

Total time required for $n$ tasks in a $k$-stage pipeline is:

$(k+n-1)\times \text{Clock cycle time}$

$=(4+1000-1)\times 165$

$=1003\times 165$

$=165495$ ns

$=165.495\ \mu sec$

Numerically, this is approximately $165.5$.

So, according to the given options, the answer is $165.5$.


Online Test Series,
Information About Examination,
Syllabus, Notification
and More.

Click Here to
View More


Online Test Series,
Information About Examination,
Syllabus, Notification
and More.

Click Here to
View More

Ask Your Question or Put Your Review.

loading...